August 16, 1962
|
Project Authorized under Public Law 87-590
|
|
August 1964
|
Construction began on Ruedi Dam
|
|
November 2, 1965
|
Started excavating Charles H. Boustead Tunnel
|
|
December 1965
|
Construction began on Sugar Loaf Dam
|
|
April 15, 1968
|
Breached old Sugar Loaf Dam
|
|
May 1968
|
Began storing water in Ruedi Reservoir
|
|
June 15, 1969
|
Charles H. Boustead Tunnel "holed through"
|
|
July 1970
|
Construction started on Pueblo Dam - first contract
|
|
May 16, 1972
|
Initial Project diversion (Chapman, South Fork, and
Fryingpan)
|
|
June 7, 1972
|
Initial diversion from Sawyer Creek
|
|
July 1972
|
Construction began on Pueblo Dam - second contract
|
|
January 9, 1974
|
Began storing water in Pueblo Reservoir
|
|
May 6, 1974
|
Initial diversion from Lily Pad
|
|
May 4, 1976
|
Initial diversion from Ivanhoe Creek
|
|
May 1977
|
First replacement water released from Ruedi Reservoir
|
|
June 1977
|
First sale of water from Ruedi Reservoir
|
|
November 22, 1977
|
Adopted the recommended bypass flow of 15 ft/s or natural
inflow, whichever is less on Lake Creek below Twin Lakes Dam
|
|
June 1, 1979
|
Initial diversion from Middle Cunningham Creek
|
|
June 4, 1979
|
Initial diversion from Mormon Creek
|
|
June 14, 1979
|
Initial diversion from North Cunningham Creek
|
|
May 8, 1980
|
Initial diversion from Hunter, Midway and No Name Creek
Diversions
|
|
June 4, 1980
|
Initial diversion from North Fork and South Cunningham
|
|
December 8, 1980
|
Federal Register notification of availability of water from
Ruedi Reservoir
|
|
April 28, 1981
|
Initial diversion from Carter
|
|
May 1, 1981
|
Initial diversion form North Fork
|
|
May 6, 1981
|
Initial diversion from Granite Creek
|
|
June 1, 1981
|
Assume operation at Twin Lakes Dam
|
|
June 23, 1981
|
Mt. Elbert Forebay filled
|
|
September 29, 1981
|
Mt. Elbert Powerplant dedicated
|
|
October 1, 1981
|
Mt. Elbert Unit #1 was made commercially available to
Western Area Power Authority for their use
|
|
May 5, 1982
|
Initial diversion from Halfmoon Creek
|
|
July 29, 1982
|
Turquoise Lake filled for first time
|
|
September 14, 1983
|
Initial diversion from south outlet works at Pueblo Dam for
Pueblo West
|
|
August 9, 1984
|
Mt. Elbert Unit #2 was made commercially available to
Western Area Power Authority for their use
|
|
May 24, 1985
|
Began storing water under Arkansas River Decree
|
|
July 1, 1985
|
Initial diversion through Fountain Valley Conduit
|
|
August 1985
|
Ruedi Hydroplant began operations
|
|
November 27, 1985
|
Twin Lakes pipeline began operations
|
|
May 7, 1986
|
Sugar Loaf Hydroplant began operations
|
|
June 1986
|
Imports restricted due to high east slope storage
|
|
November 10, 1987
|
Winter water storage decree approved and signed
|
|
November 17, 1989
|
Completed the removal of dikes and constructed the bypass
channel around the old outlet works in the old Twin Lakes dam
|
|
July 1990
|
Initial release from Twin Lakes Reservoir for recreational
benefits on the Arkansas River
|
|
August 14, 1990
|
Initial release from Ruedi Reservoir for endangered fish
(conservation flows pursuant to the biological opinion) in the Colorado's
River's "15-mile reach" for the U.S. Fish and Wildlife Service
from water leased by the Colorado Water Conservation Board
|
|
September 28, 1990
|
Dedication of Pueblo Fish Hatchery and the completion of
construction of the Fryingpan-Arkansas Project ceremony
|
|
November 1990
|
Final winter storage decree signed by court
|
|
July 21, 1992
|
Dedication of Leadville Mine Drainage Tunnel Water Treatment
Plant
|
|
September 29, 1994
|
Transfer of Phase II of the Pueblo Fish Hatchery at Pueblo
Reservoir to Colorado Division of Wildlife
|
|
May 15, 1995
|
Final transfer of recreational facilities at Pueblo to the
Department of Parks and Outdoor Recreation
|
|
July 7, 1995 |
Began storing water under Arkansas River Decree |
|
July 18, 1995 |
Began restricting imports due to high
east slope storage |
|
July 1997 |
Reservoir level at Pueblo Reservoir restricted
after a routine risk assessment of Pueblo Dam was completed and raised
concern about the foundation below the spillway section of the dam |
|
May 1999 |
Reservoir restriction lifted |
|
July 2000 |
Risk Analysis Study of Pueblo Dam completed |
|
July 11, 2000 |
Long-term contract between United States
government and the Pueblo Board of Water Works executed |
|
September 11, 2001 |
As a result of the terrorist attacks on
September 11, 2001, all Fryinpan-Arkansas Project facilities were closed to
the public. The facilities remained closed until security measures to
safeguard the federal investment were implemented. Reclamation has
maintained a heightened level of security at Fry-Ark facilities since that
time. |
|
July 23, 2002 |
Initial release of water through Pueblo Board
of Water Works south outlet works joint-use manifold |
|